Kinshire Waterline Replacement/FDR Project

The Kinshire Waterline Replacement/FDR Phase IA Project takes place in the area bounded by Sperry Avenue to the north, Poppy Avenue to the south, Clover Avenue to the west, and Patterson Irrigation District’s (PID) main canal to the east. The project scope includes replacing all water mains and water service lines for the area. Natural pipe deterioration has caused failure to the existing subsurface and asphalt pavement.  The purpose of the project is to replace aging infrastructure.  Including, full-depth reconstruction of the existing neighborhood streets, upgrading all pedestrian crosswalk ramps to meet the Americans with Disabilities Act (ADA) Standards, and any curb/gutter and sidewalk that does not allow proper gutter slope to drain effectively. Rubberized Asphalt Concrete Hot-Mix will be utilized on Clover Avenue from Kinshire Way through Sperry Avenue, on Kinshire Way from Clover Avenue through Agadoni Court, and on South 9th Street from Kinshire Way through Sperry Avenue.

Phase IA of the Kinshire Project was presented to the City Council and accepted as complete on September 20, 2022.

The Kinshire Waterline Replacement/FDR Phase IB Project
The Kinshire Waterline Replacement and Street (FDR) Project Ph IB takes place in the area bounded by Sperry Avenue to the north, Poppy Avenue to the south, Del Puerto Avenue to the west, and Patterson Irrigation District’s (PID) main canal to the east. The project scope includes replacing all water mains and water service lines for the area. The purpose of the project is to replace aging infrastructure. Natural pipe deterioration has caused failure to the existing subsurface and asphalt pavement. Therefore, this project will include water main, services (existing meters to remain in place and utilized), full-depth reconstruction of the existing neighborhood streets, upgrading all pedestrian crosswalk ramps to meet the American with Disabilities Act (ADA) Standards, and any curb/gutter and sidewalk that does not allow proper gutter slope to drain effectively.

Project Status
The construction of Phase IB was awarded to United Pavement Maintenance, Inc. 
Unfortunately, the COVID pandemic has affected our contractor's ability to procure materials. The inability to secure the necessary materials needed to complete this project has caused delays. Phase 1 of Kinshire IB was completed in September of 2022, and the construction of Phases 2 and 3 will be delayed until March of 2023. Road closures and project updates will continue to be posted on the City of Patterson’s website.

When construction resume, notices will be provided 5 business days in advance to those who will be affected by delays and disruption of services.If you have any questions or concerns regarding this project, please contact me at (209) 895-8033. 

Thank you for your continued patience and understanding.

City of Patterson